Anthony Wayne Bridge Rehabilitation — E.S. Wagner project photo

Our Work / Projects / ANTHONY WAYNE BRIDGE REHABILITATION — HIGH-LEVEL SUSPENSION BRIDGE CONSTRUCTION

ANTHONY WAYNE BRIDGE REHABILITATION — HIGH-LEVEL SUSPENSION BRIDGE CONSTRUCTION

Sector

Transportation

Client

Ohio Department of Transportation (ODOT)

Location

Toledo, OH

State

Ohio

Status

Complete

By the Numbers

Metrics

1,252 LF

Suspension Span Rehabilitation

8550 CY

Structural Concrete

1,040,000 LBS

Structural Steel

1,490,000 LBS

Reinforcing Steel

Challenge

Rehabilitating ODOT’s only suspension bridge required replacing the bridge deck, performing extensive structural steel repairs, and reconstructing critical spans while maintaining the stability of the historic suspension system. The work demanded highly specialized construction sequencing, custom temporary support systems, and rapid turnaround of steel repairs, all within a fixed 570-day closure schedule.

Solution

In order to comply with balanced suspension span loading requirements, E.S. Wagner deployed two specialized bridge crews, outfitted with the same complement of equipment, and ensured that each progressed away from the center of the suspension span at exactly the same rate while performing structural steel and deck replacement. Innovative engineering facilitated highly complex main suspension cable hold-down retrofits, high-capacity cable jacking, and demolition adjacent to critical suspension components. Meticulous phase-by- phase planning accelerated critical steel repair fabrication, allowing the team to safely complete these high-risk and sequential operations and reopen the bridge to traffic 26 days ahead of schedule.

Anthony Wayne Bridge Rehabilitation — E.S. Wagner project photo

Project Scope

E.S. Wagner Company served as the prime contractor for the multi-year rehabilitation of the Anthony Wayne Bridge, ODOT’s only remaining suspension bridge, spanning the Maumee River in Toledo, Ohio. Effectively three types of bridges in one structure, the project included complete replacement of the bridge deck across the 1,252-foot suspension spans, extensive structural steel repairs, rehabilitation of concrete substructures, demolition and replacement of two 200-foot truss spans, and complex upgrades to the bridge’s main cable hold- down system. Work required the installation of a custom suspended work platform, placement of lightweight concrete decks, erection of over 1,000,000 pounds of new structural steel, and execution of highly specialized repairs while maintaining the structural integrity of the suspension system by perfectly balancing side-to-side loading and progress. Through complex engineering coordination, detailed construction sequencing, accelerated structural steel repair identification and fabrication, and careful scheduling and resource allocation that all but eliminated overtime on this labor-intensive project, E.S. Wagner completed the rehabilitation and reopened the bridge to traffic, utilizing only 544 of the allotted 570-day close period.

Keep Exploring

Related Projects

  • I75 - I475 (US23) Interchange — E.S. Wagner project photo

    I-75/I-475 (US 23) INTERCHANGE — I-75 RECONSTRUCTION AND WIDENING

    Perrysburg, OH

    316,800 SY

    9” Concrete Pavement Removal

    206,000 TN

    Aggregate/Granular Embankment

  • I-75 Downtown Toledo — E.S. Wagner project photo

    I-75 DOWNTOWN TOLEDO — I-75 RECONSTRUCTION

    Toledo, OH

    33,000 CY

    of Structural Concrete

    21,503,447

    lbs. of Structural Steel Erected

  • GREENBELT PARKWAY — NEW ROAD CONSTRUCTION PH I & II — E.S. Wagner project photo

    GREENBELT PARKWAY — NEW ROAD CONSTRUCTION PH I & II

    Toledo, OH

    384,000

    Tons Solid Waste Removal

    2.2M

    Gallons Regulated Water Management

From Proof to Partnership

Have a Project Like This?

Bring us your site and scope — we'll show you how E.S. Wagner delivers it.