NATIONAL LIME AND STONE — STRIPPING PROJECTS
By the Numbers
Metrics
12.3M CY
Excavation
Challenge
Over a 20-plus year period, performing numerous projects, all demanding large-scale excavation, typically in wintertime conditions. Coordinating efficient haul routes and material placement while maintaining stable site conditions and quick recovery from weather events, while allowing for uninterrupted quarrying operations.
Solution
Committing significance equipment resources to reduce schedule duration, while stablishing well- planned haul routes and ramps to maximize efficiency and safety. Implementing proactive water management controls, such as temporary drainage systems and ditching, to keep excavation areas stable and operational. Working with National Lime and Stone to match the quarrying and stripping plans to maximize the productivity of both operations.

Project Scope
E.S. Wagner Company performed numerous stripping operations for National Lime and Stone to support quarry development and access to underlying resources. The projects included mobilization of personnel and equipment, followed by clearing and grubbing to prepare the sites for excavation. Temporary water management measures were implemented, including drainage tile intercepts and constructed ditches to maintain safe and efficient working conditions. Haul ramps were strategically placed and carefully constructed to facilitate challenging access to overburden walls and maximize productivity. The primary scopes involved the removal of overburden materials to expose usable rock deposits. Excavated materials were hauled to designated areas for stockpiling or reuse as engineered fill. Placement of fill and construction of dikes were completed to support site grading and long-term stormwater control.
On the Ground
Project Gallery
Final photography, captions, and any video to be supplied by ESW per project.
Keep Exploring
Related Projects
-

TOLEDO MUD HENS STADIUM — SITE DEVELOPMENT, DEEP FOUNDATIONS, AND SHORING
Toledo, OH
63K SF
Permanent and Temporary Steel Sheet Piling
2400 FT
36” Drilled Shaft Foundations
-

OHIO CAT EQUIPMENT AND PARTS FACILITY — ENTRANCE DRIVE AND SITEWORK
Perrysburg, OH
90K CY
Earthwork
16K LF
Utilities (Waterline, Sanitary sewer, and Storm Sewer)
-

INTERSTATE CHEMICAL — PROCESS PLANT SITE DEVELOPMENT
Oregon, OH
9,000 CY
Structural Concrete
12,000 SY
10” Concrete Pavement