WASTE MANAGEMENT — EVERGREEN LANDFILL CELL 11 — CELL EXCAVATION, LINER CONSTRUCTION, CAPPING, — AND SEDIMENT POND
By the Numbers
Metrics
1.1M CY
Earthwork Excavation
22.5
Acres of New Landfill Cells
4-Acre
Sedimentation Pond
7
Acres of Final Cap
120K CY
Compacted Clay Liners
Challenge
Constructing multiple landfill expansion components with complex liner and leachate collection systems while working within the unique design requirements of the Evergreen RDF Facility.
Solution
E.S. Wagner delivered four separate projects consisting of new landfill cells, closures, and leachate and run-off control features. Success required substantial resource commitment, leveraging innovative construction methods, the application of extensive earthwork and landfill construction expertise, and the coordinated installation of complex liner, drainage, and leachate collection systems.

Project Scope
Waste Management retained E.S. Wagner Company to construct 22.5 acres of new landfill cells, a 4-acre sedimentation pond, and 7 acres of final cap at the Evergreen RDF Facility in Northwood, Ohio. Over a three-year period, ESW performed approximately 1.1 million cubic yards of mass excavation and utilized 120,000 cubic yards of on-site clay to construct recompacted clay liners. The project featured 975 linear feet of 2:1 side slopes, requiring ESW to develop an innovative approach in order to place compacted clay liner on these very steep slopes while maintaining quality. Following earthwork completion, ESW installed approximately 980,000 square feet of 60- mil HDPE geomembrane liner, 75,000 cubic yards of shredded tires for drainage, 2,800 linear feet of 6-inch HDPE leachate collection pipe, and 390 linear feet of 24-inch HDPE slope risers serving three leachate collection sumps. Additional work included 250,000 cubic yards of excavation for a 4-acre sedimentation pond and installation of 1,250 linear feet of 30-inch CMP storm sewer.
On the Ground
Project Gallery
Final photography, captions, and any video to be supplied by ESW per project.
Keep Exploring
Related Projects
-

LIMA UP GROUND RESERVOIR
Allen County, OH
4.5M CY
Moisture Conditioned Embankment
90K TN
Slope Protection
-

HOFFMAN ROAD LANDFILL — CELL AND LINER CONSTRUCTION – CITY OF TOLEDO
Toledo, OH
515K CY
New Cell Excavation
53K CY
Compacted Clay Liner
-

ALLIED WASTE LANDFILL — NEW CELL CONSTRUCTION & WASTE RELOCATION
Carey, OH
470K CY
Waste Relocation
215K CY
Excavation